24
Programs
683
Projects
Section | Original Allocation | Adjusted Allocation1 | Committed2 | Balance3 |
---|---|---|---|---|
$4,090,000,000 | $4,090,000,000 | $4,060,560,167 | $29,439,832 | |
Section 5096.821 State plan of flood control | $3,000,000,00 | $2,926,650,367 | $2,882,768,768 | $43,881,598 |
Section 5096.824 Flood control and flood prevention projects | $500,000,000 | $487,775,061 | $482,396,310 | $5,378,751 |
Section 5096.825 Flood protection corridors and bypasses | $290,000,000 | $282,909,535 | $274,184,715 | $8,724,820 |
Section 5096.827 Storm water flood management | $300,000,000 | $292,665,037 | $289,474,811 | $3,190,226 |
Section 5096.953 et seq. Statewide Bond Cost | $0 | $0 | $31,735,563 | ($31,735,563) |
Reallocated to Proposition 1 | $0 | $100,000,000 | $100,000,000 | $0 |
(1) "Adjusted Allocation" reflects the "Original Allocation" less an adjustment mandated by Prop 1 distributed across all program chapters.
(2) "Committed" means the amount appropriated, the amount proposed for appropriations, or amount committed in out years.
(3) "Balance" equals Chapter Balance plus Chapter Set Asides as found on the Summary for Chapters in the Allocation Balance Report.
(2) "Committed" means the amount appropriated, the amount proposed for appropriations, or amount committed in out years.
(3) "Balance" equals Chapter Balance plus Chapter Set Asides as found on the Summary for Chapters in the Allocation Balance Report.