Project: County of Shasta - CSA6-Jones Valley Water Meter Replacement, Backwash Pump Installation and SCADA Improvement Project

Description: The Project is to install approximately 393 automatic meter readers. In addition, the Project will increase system efficiency by installing a backwash pump to ensure adequate cleaning of the pressure filters and SCADA system to allow remote monitoring at the water treatment plant located near Shasta Lake.

Reference Number: 3940P68D2002035

Implemented By: County of Shasta

Objective:

Type: Infrastructure Improvement

Total Cost: $793,000.00

Project Status: Project Implementation

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 3/1/2024    Actual Completion:

Associated Counties: Shasta

Located In Severely Disadvantaged Community: Yes

Contribution SourcesContribution DateContribution Amount
  $793,000.00
Prop. 68, Water Quality/Safe Drinking Water Program4/1/2021$793,000.00


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementWater Quality Infrastructure  