Skip to Main Content
Menu
Contact Us

Project: Caruthers CSD - Water System Improvements - New Well No. 7 - Construction Project

Description: The Projet will drill a new well and construct site facilities includeing a well pujmp, hydropneumatic tank, piping, motor control center, generator, transformer, and site fencing. A new transmission pipeline will be installed from Well No. 7 to the Well No. 6 site for treatment and/or blending.

Reference Number: 3940P68D2002013

Implemented By: Caruthers CSD

Objective:

Type: Water Management

Total Cost: $2,922,000.00

Project Status: Project Implementation

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 3/1/2023    Actual Completion:

Associated Counties: Fresno

Located In Severely Disadvantaged Community: Yes

Contribution SourcesContribution DateContribution Amount
  $2,922,000.00
Prop. 68, Water Quality/Safe Drinking Water Program11/17/2020$2,922,000.00


Project MetricMetric TopicQuantityUnit
Water ManagementOther  

Location

loading loading