Project: Special Projects Magnetic Anomaly Grand Island, RD 3

Description: Inspection and evaluation of levees surrounding Island using electromagnetic anomaly subsurface techniques.

Reference Number: 3860-P84-775

Implemented By: RD 3 Grand Island

Objective: Identify potential Levee problems to prevent levee failure from unseen sources

Type: Infrastructure Improvement

Total Cost: $99,893.00

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 9/1/2008    Actual Completion: 6/17/2009

Associated Counties: Sacramento

Located In Disadvantaged Community: No

Contribution SourcesContribution DateContribution Amount
  $99,893.00
Federal Contribution12/29/2011$67,428.00
Local Contribution10/3/2016$9,989.03
Prop. 84, Delta Levees System Integrity Program10/3/2016$22,475.97


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementOther  