Project: Alameda Creek Zone 5 Line LLCR

Description: The project consisted of repairs to three levee segments. Segment FC5-173 suffered underseepage problems and a sheet pile cutoff wall was implemented to eliminate seepage issues. A soil bentonite cutoff wall was implemented at segment FC5-209 to address underseepage in that location. Lastly, at site FC5-205, the levee was raised due to insufficient freeboard and rock slope protection was implemented to address erosion.

Reference Number: 3860-P84-712

Implemented By: Alameda County Flood Control and Water Conservation District

Objective: Flood protection.

Type: Restoration, Infrastructure Improvement

Total Cost: $8,482,413.82

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 12/30/2014    Actual Completion: 1/31/2015

Associated Counties: Alameda

Located In Disadvantaged Community: No

Contribution SourcesContribution DateContribution Amount
  $8,482,413.82
Local Contribution2/5/2014$4,241,000.00
Prop. 84, Local Levee Assistance Program7/1/2007$4,241,413.82


Project MetricMetric TopicQuantityUnit
RestorationErosion Control  
Infrastructure ImprovementLevee Repair, Strengthen, Raised0.6miles of levee repaired/strengthened