Project: 5-year Plan (BIMID) Bethel Island BI 09-1.0

Description: Continued from FY 2008-09 Budget, Projects to reimburse RDs for estimating repair plans to achieve Delta Standards and maintain Marsh Levees

Reference Number: 3860-P84-358

Implemented By: Bethel Island MID

Objective: To provide an assessment of the district's existing levee system and a strategic plan to meet a desired level of protection.

Type: Infrastructure Improvement

Total Cost: $50,872.00

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: No

Estimated Completion: 12/31/2011    Actual Completion: 9/15/2013

Associated Counties: Contra Costa

Located In Disadvantaged Community: Yes

Contribution SourcesContribution DateContribution Amount
  $50,872.00
Other State Funds7/14/2014$47.16
Prop. 84, Delta Levees System Integrity Program6/22/2009$50,824.84


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementOther  