Project: Middle River Intake and Pump Station (formerly known as Alternative Intake Project)

Description: Construct a new pump station, a concrete intake structure, and pipe across Victoria Island with tunneling beneath Old River to the District's Old River Pump Station.

Reference Number: 3860-P84-221

Implemented By: Contra Costa Water District

Objective: The alternative intake enabled CCWD to relocate some of its diversions to a Delta location with better source water quality than was available at CCWD's Old River and Rock Slough intakes. It allowed CCWD to divert higher quality water while not increasing the amount of water pumped from the Delta (rate or annual quantity).

Type: Infrastructure Improvement

Total Cost: $99,000,000.00

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 5/10/2011    Actual Completion: 5/10/2011

Associated Counties: Contra Costa, San Joaquin

Located In Disadvantaged Community: Yes

Contribution SourcesContribution DateContribution Amount
  $99,000,000.00
Federal Contribution11/2/2011$70,105,262.00
Prop. 84, Delta Water Quality Program9/9/2010$28,894,738.00


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementWater Quality Infrastructure  