Project: Delta Aqueduct Interties

Description: SBX2 1 -EBMUD Interconnection of municipal and industrial aqueduct that cross the Sacramento-San Joaquin delta.

Reference Number: 3860-P84-066

Implemented By: East Bay Municipal Utility District

Objective: Construct improvements to the Mokelumne Aqueducts so they are less vulnerable to levee failures and flooding in the Delta that may occur due to levee instability resulting from high water levels, weakness in levee construction, physical damage from burrowing animals, seepage, subsidence, island dewatering or farming activities, weaknesses in foundation soils, or seismic events.

Type: Infrastructure Improvement

Total Cost: $10,000,000.00

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 9/4/2014    Actual Completion: 7/9/2014

Associated Counties: Contra Costa, San Joaquin

Located In Disadvantaged Community: Yes

Contribution SourcesContribution DateContribution Amount
  $10,000,000.00
Prop. 84, Integrated Regional Water Management10/6/2009$10,000,000.00


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementOther  