Project: Special Projects - GW-08-1.0 - Grizzly West

Description: Construction of Grizzly Island Levee Improvement Project.

Reference Number: 3860-P84-011

Implemented By: RD 2136 - Grizzley Island

Objective: Rehabilitation of levees in the Delta to protect water conveyance and water quality

Type: Infrastructure Improvement

Total Cost: $113,333.00

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 12/31/2008    Actual Completion: 12/31/2008

Associated Counties: Solano

Located In Disadvantaged Community: No

Contribution SourcesContribution DateContribution Amount
  $113,333.00
Local Contribution6/25/2014$28,333.00
Prop. 84, Delta Levees System Integrity Program4/10/2008$85,000.00


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementLevee Repair, Strengthen, Raised0.15miles of levee repaired/strengthened