Project: Flood System Maintenance Policy and Procedures Development, Review, and Enforcement

Description: Evaluation of the entire State-Federal Flood Control System is needed to identify areas with chronic Operation and Maintenance (O&M) issues and action needs to be taken to correct the issues using enhanced O&M standards. There is a need to develop and evaluate more comprehensive and enhanced O&M standards for the facilities of the State Plan of Flood Control. These efforts will include addressing environmental protection and the enhancement and management of BMP's that include adaptive management approaches. The standards and guidelines will be reviewed and updated periodically to ensure FloodSAFE continually brings best-in-class practices and technologies to the State's flood management.

Reference Number: 3860-P1E-488

Implemented By: Department of Water Resources

Objective: Improved flood protection.

Type: Research/Planning (including Science)

Total Cost: $10,416,442.00

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 6/30/2020    Actual Completion:

Associated Counties: Butte, Colusa, Fresno, Glenn, Lake, Madera, Merced, Placer, Plumas, Sacramento, San Joaquin, Solano, Stanislaus, Sutter, Tehama, Yolo, Yuba



Contribution SourcesContribution DateContribution Amount
  $10,416,442.00
Prop. 1E, Flood System Evaluation and Rehabilitation Program1/29/2014$10,416,442.00


Project MetricMetric TopicQuantityUnit
Research/Planning (including Science)Other  

Location