Project: Spring 2012 Special Projects Hazard Mitigation Plan PSP - SB855 - RD 2044 - King Island

Description: Improve local agency levees to meet the HMP standard as described in the MOU signed between the FEMA and CalEMA in February 2010.

Reference Number: 3860-P1E-388

Implemented By: RD 2044- King Island

Objective: Delta Levee Maintenance and Improvement

Type: Infrastructure Improvement

Total Cost: $967,098.19

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 8/30/2017    Actual Completion: 6/30/2017

Associated Counties: San Joaquin



Contribution SourcesContribution DateContribution Amount
  $967,098.19
Local Contribution7/15/2015$96,709.82
Prop. 1E, Delta Levees System Integrity Program8/12/2013$870,388.37


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementLevee Repair, Strengthen, Raised6.1miles of levee repaired/strengthened