Project: Haster Retarding Basin and Haster Pump Station

Description: The Project consists of: (1) Increase the storage capacity of Haster Basin to accommodate large storm events by pumping out water from the Basin during the early portion of storm events to increase capacity during the peak of the storm. The 100-year flow rate expected into Haster Basin is 2,200 cubic feet per second and the downstream channel capacity is 460 cubic feet per second; without the proposed pump station, overbank flow would flood the homes surrounding the basin; (2) Increase the capacity of the downstream reach of the East Garden Grove Wintersburg Channel by reconstructing the outlet channel within the specified reach.

Reference Number: 3860-P1E-358

Implemented By: County of Orange

Objective: Manage stormwater runoff to reduce flood damage and where feasible, provide other benefits, including groundwater recharge, water quality improvement, and ecosystem restoration.

Type: Water Management

Total Cost: $31,354,199.99

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 12/31/2015    Actual Completion: 10/14/2015

Associated Counties: Orange



Contribution SourcesContribution DateContribution Amount
  $31,354,199.99
Local Contribution2/3/2012$15,677,100.00
Prop. 1E, Stormwater/Flood Management12/6/2016$15,677,099.99


Project MetricMetric TopicQuantityUnit
Water ManagementStormwater Flood / Capture  

Location