Project: West Fontana Channel Stormwater Flood Reduction Project

Description: The project will expand and line the existing West Fontana Channel. The project will capture peak stormwater flows to provide enhanced flood protection from 100-year flood events for approximately 300 acres and provide secondary water quality beneficial uses. Construction will include: channel deepening and concrete lining, box culverts, stub outs, low flow bio-swale and other associated improvements.

Reference Number: 3860-P1E-350

Implemented By: City of Fontana

Objective: Expand and line an existing channel to provide enhance flood protection.

Type: Water Management

Total Cost: $35,750,000.00

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 12/31/2020    Actual Completion: 2/23/2021

Associated Counties: San Bernardino



Contribution SourcesContribution DateContribution Amount
  $35,750,000.00
Local Contribution2/3/2012$25,800,000.00
Prop. 1E, Stormwater/Flood Management12/21/2011$9,950,000.00


Project MetricMetric TopicQuantityUnit
Water ManagementStormwater Flood / Capture  

Location