Project: Stormwater Source Control in the CABY Region

Description: The Project involves the construction of green infrastructure at two public sites and will include five rain gardens, three vegetated bio-swales with underground retention system, pervious pavement parking, walkways and assembly areas with interpretive signs, and two retention wetlands. These features will capture and treat 8.4 million gallons of runoff annually, and will provide outreach and education for thousands of visitors.

Reference Number: 3860-P1E-347

Implemented By: American Rivers

Objective: Manage stormwater runoff to reduce flood damage and where feasible, provide other benefits, including groundwater recharge, water quality improvement, and ecosystem restoration.

Type: Recreation/Access/Interpretation, Water Management

Total Cost: $1,019,207.56

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 4/30/2018    Actual Completion: 1/31/2019

Associated Counties: Nevada



Contribution SourcesContribution DateContribution Amount
  $1,019,207.56
Federal Contribution2/3/2012$375,000.00
Local Contribution2/3/2012$135,000.00
Prop. 1E, Stormwater/Flood Management4/19/2019$509,207.56


Project MetricMetric TopicQuantityUnit
Recreation/Access/InterpretationDemonstration/Interpretive Programs  
Water ManagementStormwater Flood / Capture  

Location

loading loading