Project: FY 09-10 Aqueduct Project #2 (RD 2072) - Woodward Island WD 10-2

Description: Improve levees at two areas including Design & construction: 1) 10,100 ft.(1.9 mi) slope improvements to PL 84-99 standard including habitat enhancement and 2) 22,500 ft (4.3 mi) raising levee crown elevation to PL 84-99 standards and extending slope improvements to a total of 24,500 ft (4.6 mi)

Reference Number: 3860-P1E-192

Implemented By: Reclamation District 2072 Woodward Island

Objective: Reinforce sections of levees that have the highest potential to suffer breaches or failure and cause harm to municipal and industrial water supply aqueducts that cross the Delta.

Type: Infrastructure Improvement

Total Cost: $4,971,193.82

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: No

Estimated Completion: 6/30/2013    Actual Completion: 2/15/2013

Associated Counties: San Joaquin



Contribution SourcesContribution DateContribution Amount
  $4,971,193.82
Local Contribution7/15/2016$745,679.07
Other State Funds7/15/2016$8,155.00
Prop. 1E, Delta Levees System Integrity Program7/15/2016$4,217,359.75


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementLevee Repair, Strengthen, Raised4.87miles of levee repaired/strengthened