Project: FY 09-10 Aqueduct Project #1 (RD 2039) - Upper Jones Tract-UJ 10-1

Description: Improve levees at three areas including Design and construction: 1) 19,500 ft (3.7 mi) to State's Hazard Mitigation Plan (HMP) minimum standard, 2) 9,600 ft.(1.8 mi) improving levee slopes to US Army Corps of Engineers PL 84-99 standards, including 5,700 ft.(1.1 mi) building PL 84-99 stability berm, 3) 9,600 ft (1.8 mi) improving levees to PL 84-99 slope standards and, 8,900 (1.7 mi) building PL 84-99 stability berm.

Reference Number: 3860-P1E-189

Implemented By: Reclamation District 2039-Upper Jones Tract

Objective: Reinforce sections of levees that have the highest potential to suffer breaches or failure and cause harm to municipal and industrial water supply aqueducts that cross the Delta.

Type: Infrastructure Improvement

Total Cost: $2,456,577.34

Project Status: Project Implementation

On Time?: Yes    Within Scope?: Yes    Within Budget?: No

Estimated Completion: 12/31/2018    Actual Completion: 1/10/2020

Associated Counties: San Joaquin



Contribution SourcesContribution DateContribution Amount
  $2,456,577.34
Local Contribution10/26/2017$517,000.00
Prop. 1E, Delta Levees System Integrity Program5/30/2018$1,939,577.34


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementLevee Repair, Strengthen, Raised3.69miles of levee repaired/strengthened