Project: Folsom Dam Raise Project, Bridge Element

Description: The bridge element is a separable element of the larger Folsom Dam Raise Project. The bridge element was completed first so that the Folsom Dam Modification, Join Federal Project, can proceed accordingly. Also, the new bridge redirects traffic off of the dam for security reasons and also facilitates raising the dam. The Folsom Dam 3.5 ft Raise Project itself is still in design stage, as of Feb 2017, which will be constructed in the project under another project heading - "Folsom Dam Raise Project". Total project cost amount below includes State support costs for the bridge construction only.

Reference Number: 3860-P1E-042

Implemented By: Department of Water Resources

Objective: The new Folsom Dam Bridge redirects traffic off of the dam for security reasons and assists in flood protection.

Type: Infrastructure Improvement

Total Cost: $102,499,609.45

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 12/1/2010    Actual Completion: 12/1/2010

Associated Counties: Sacramento



Contribution SourcesContribution DateContribution Amount
  $102,499,609.45
Federal Contribution5/22/2017$99,755,000.00
Prop. 1E, USACE Projects5/22/2017$2,744,609.45


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementOther  