Project: Folsom Dam Raise - DA

Description: The Sacramento metropolitan area is considered among the highest flood risks in the nation, and flooding in the area could impact upwards of 440,000 people and impact an estimated $58 billion in property. The Folsom Dam Raise project consists of the selected 3.5 feet raise of Folsom Dam and reservoir dikes, reconfiguring the Folsom Dam penstocks, ecosystem restoration projects, and the construction of a bridge below Folsom Dam, which has now been completed. Detailed design on the Folsom Raise project is scheduled to be completed in 2015, proceeding in conjunction with the Folsom Dam Modifications Joint Federal Project to ensure the optimum performance and identification of shared opportunities between two projects. Total project amount includes State support costs for project implementation.

Reference Number: 3860-P1E-041

Implemented By: Department of Water Resources

Objective: Flood protection will be increased by raising the dam 3.5 feet.

Type: Infrastructure Improvement

Total Cost: $27,029,984.79

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 3/1/2021    Actual Completion:

Associated Counties: Sacramento



Contribution SourcesContribution DateContribution Amount
  $27,029,984.79
Federal Contribution8/2/2019$18,876,814.29
Local Contribution8/2/2019$1,982,065.50
Prop. 1E, USACE Projects5/22/2017$6,171,105.00


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementDam Modification  

Location