Project: Butte Slough Outfall Gates Rehabilitation

Description: Rehabilitate the outfall gates by repairing known structural deficiencies, replacing worn out appurtenances, constructing a trash barrier system to protect the gates and ease debris collection, and upgrading the electrical and communication system to include backup capability to meet current USACE O&M standards.

Reference Number: 3860-P1E-024

Implemented By: Department of Water Resources

Objective: To repair and/or replace this flood control structure to ensure proper operations, maintenance, and readiness in the event of emergencies and that facilities function as designed.

Type: Infrastructure Improvement

Total Cost: $21,615,604.45

Project Status: Project Implementation

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 6/30/2022    Actual Completion:

Associated Counties: Colusa, Sutter



Contribution SourcesContribution DateContribution Amount
  $21,615,604.45
Other State Funds11/23/2021$14,000,000.00
Prop. 1E, Flood Control Facilities Evaluation and Rehabilitation Program11/18/2021$7,615,604.45


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementPermanent Operable Barriers  