Project: Salyer MWC (Formerly Riverview Acres WS)

Description: Feasibility Study proposes to drill up to four (4) test wells to determine whether a new groundwater source may be developed for the system. If it is determined that the test well(s) can produce groundwater of sufficient quality and quantity, plans and specifications for the production well(s), new storage tanks (2), transmission line, chlorination facilities, and a pump station (if necessary) will be prepared. Successful development of a groundwater source will eliminate the surface water source and the requirement for treatment.

Reference Number: 3940P8411C80

Implemented By: Salyer Mutual Water Company, Salyer Mutual Water Compnay

Objective: Funding of a project, which includes engineering design, to identify options to address and resolve water quality issues

Type: Research/Planning (including Science)

Total Cost: $125,273.75

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 9/21/2014    Actual Completion: 9/18/2014

Associated Counties: Trinity

Located In Disadvantaged Community: Yes

Contribution SourcesContribution DateContribution Amount
  $125,273.75
Prop. 84, Small Community Infrastructure Improvements Program8/12/2013$91,115.16
Prop. 84, Small Community Infrastructure Improvements Program3/25/2015$34,158.59


Project MetricMetric TopicQuantityUnit
Research/Planning (including Science)Other  

Location