Project: Gratton School

Description: The proposed alternatives for this project are consolidating with a neighboring water system, drilling a new well, and installing arsenic treatment on the existing well. This feasibility study will include the following tasks: developing a consolidation feasibility study report, contracting a labor compliance consultant, developing final plans and specifications for selected construction project alternative, and preparing CEQA documentation.

Reference Number: 3940P8412C97

Implemented By: Gratton School District

Objective: Funding of a project, which includes engineering design, to identify options to address and resolve water quality issues

Type: Research/Planning (including Science)

Total Cost: $183,585.50

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 5/28/2014    Actual Completion: 6/2/2014

Associated Counties: Stanislaus

Located In Disadvantaged Community: No

Contribution SourcesContribution DateContribution Amount
  $183,585.50
Prop. 84, Small Community Infrastructure Improvements Program8/12/2013$173,349.00
Prop. 84, Small Community Infrastructure Improvements Program3/26/2015$10,236.50


Project MetricMetric TopicQuantityUnit
Research/Planning (including Science)Other  