Project: LADWP North Hollywood Remediation - Construction Project

Description: This project is for the purpose of implementing an interim response action through the use of groundwater extraction at remediation wells and the construction of a groundwater treatment facility that will include Ultraviolet Advanced Oxidation Process treatment to provide cleanup of volatile organic compounds (VOCs) and 1,4-dioxane impacted groundwater that is migrating to the Rinaldi-Toluca Well Field located within the San Fernando Groundwater Basin.

Reference Number: 3940P01D1912533

Implemented By: LADWP North Hollywood

Objective: Construct an UV AOP system to treat VOCs & 1,4-dioxane impacted groundwater in the Rinaldi-Toluca Well Field.

Type: Water Management

Total Cost: $189,660,719.00

Project Status: Project Implementation

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 1/31/2023    Actual Completion:

Associated Counties: Los Angeles

Project Benefits a Disadvantaged Community (or SDAC): No

Contribution SourcesContribution DateContribution Amount
  $189,660,719.00
Other State Funds6/24/2020$94,830,360.00
Prop. 1, Groundwater Sustainability6/24/2020$94,830,359.00


Project MetricMetric TopicQuantityUnit
Water ManagementGroundwater Remediation  

Water Action Plan Target

    
Provide Safe Water for All CommunitiesAction Description