Project: In-Line Storm Drain Runoff Infiltration Demonstration Project

Description: Installing stand-alone treatment and infiltration systems within existing storm drain lines and catch basins.

Reference Number: 394011101554

Implemented By: City of Santa Monica

Objective: Installing stand-alone treatment and infiltration systems within existing storm drain lines and catch basins.

Type: Infrastructure Improvement

Total Cost: $380,663.08

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 9/30/2014    Actual Completion: 1/2/2015

Associated Counties: Los Angeles

Located In Disadvantaged Community: No

Contribution SourcesContribution DateContribution Amount
  $380,663.08
Private Contribution8/12/2013$100,000.00
Prop. 84, Clean Beaches Grant Program8/12/2013$280,663.08


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementOther  