Project: Porter Creek Stream Flow Enhancement Project, Phase II

Description: Project will build on Porter Creek phase I (implementation of flow release system), conduct scientific studies and install a permanent stream flow gauge to inform an operations schedule and Long Term Stream Flow Enhancement Plan.

Reference Number: 36402019030

Implemented By: University of California, Berkeley

Objective:

Type: Water Management

Total Cost: $779,365.00

Project Status: Project Implementation

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 3/31/2022    Actual Completion:

Associated Counties: Sonoma

Project Benefits a Disadvantaged Community (or SDAC): Yes

Contribution SourcesContribution DateContribution Amount
  $779,365.00
Local Contribution4/4/2019$14,551.00
Other State Funds4/4/2019$132,414.00
Private Contribution4/4/2019$102,034.00
Prop. 1, Stream Flow Enhancement4/4/2019$530,366.00


Project MetricMetric TopicQuantityUnit
Water ManagementConveyance  

Water Action Plan Target

    
Protect and Restore Important EcosystemsAction Description