Project: Heisler Park ASBS Protection & Preserve Project Phase III

Description: This project will eliminate the majority of runoff to the ASBS through the use of site design and structural BMPs. BMPs are the regrading and recontouring of the land within the project boundaries to direct storm flows away from the ASBS and the reduction of hardscape area to increase site permeability. The innovative site design includes curbed and tilted pathways, contoured swales and terraces built with retaining walls to contain sediments and push surface flows into structural and treatment control BMPs. The treatment control BMPs are vegetated areas where flows will infiltrate for plant use and be filtered through vegetation to remove nutrients and bacteria. Structural BMPs include catch basin filter inserts. The combination of BMPs should be adequate to treat all flows but major rain events. Smarttimers, water efficient sprinkler heads and drought tolerant vegetation will reduce or eliminate nuisance flows by reducing on-site water waste.

Reference Number: 394010410550

Implemented By: City of Laguna Beach

Objective: Eliminate the majority of runoff to the Heisier Park ASBS and treating any remaining water with BMPs prior to discharge

Type: Restoration

Total Cost: $3,760,000.00

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 3/31/2013    Actual Completion: 12/20/2013

Associated Counties: Orange

Located In Disadvantaged Community: No

Contribution SourcesContribution DateContribution Amount
  $3,760,000.00
Private Contribution8/12/2013$1,260,000.00
Prop. 84, Clean Beaches Grant Program8/12/2013$2,500,000.00