Skip to Main Content
Menu
Contact Us

Project: Trinidad Pier Reconstruction

Description: Construction of a new pier that will capture runoff, which currently drains into the ASBS, and channel it to a land-based, filter-protected infiltration gallery. Creosote-coated piles will be removed and replaced by polymer-coated steel-cast concrete piles, which will eliminate the leaching of pollutants into the ASBS.

Reference Number: 394010409550

Implemented By: City of Trinidad

Objective: Demolition of the existing wooden pier and construction of a new concrete pier, to eliminate the leaching of pollutants into the ASBS.

Type: Infrastructure Improvement

Total Cost: $2,779,258.50

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 3/1/2014    Actual Completion: 5/5/2014

Associated Counties: Humboldt

Located In Disadvantaged Community: Yes

Contribution SourcesContribution DateContribution Amount
  $2,779,258.50
Private Contribution8/12/2013$280,000.00
Prop. 84, Clean Beaches Grant Program8/12/2013$2,499,258.50


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementWater Quality Infrastructure  

Location

loading loading