Project: Winship-Robbins Elementary School Well #3 - Construction Project

Description: During the feasibility study, WRESD drilled a test hole to obtain more information about the groundwater quality of water-producing zones. Two zones were identified as producing water with arsenic concentrations below the arsenic MCL. The construction project includes the development of the test hole into a production well, and connecting the new groundwater source, Well #2, to the school’s existing water system. The school’s existing well, Well #1, will remain and be maintained as a backup emergency source.

Reference Number: 3940P01D1702095

Implemented By: Winship-Robbins Elementary School District

Objective: The Project will bring the water system into compliance with the arsenic maximum contaminant level. The Project includes the development of a production well, and the connection of the new well to the school’s existing potable water system.

Type: Infrastructure Improvement

Total Cost: $350,000.00

Project Status: Project Implementation

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 3/1/2022    Actual Completion:

Associated Counties: Sutter

Project Benefits a Disadvantaged Community (or SDAC): Yes

Contribution SourcesContribution DateContribution Amount
  $350,000.00
Prop. 1, Water System Infrastructure Improvements - Safe Drinking Water6/22/2018$350,000.00


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementOther  

Water Action Plan Target

    
Provide Safe Water for All CommunitiesAction Description