Project: Big Canyon Creek Restoration and Estuary Adaptation

Description: The project will conduct feasibility studies, develop project designs, and complete permitting and environmental compliance for the restoration and enhancement of Big Canyon Creek and the restoration of tidal transition zones for wetland migration in the future.

Reference Number: 37601701801

Implemented By: Newport Bay Conservancy

Objective: wetland restoration and enhancement

Type: Research/Planning (including Science)

Total Cost: $638,604.45

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 1/25/2021    Actual Completion: 9/17/2020

Associated Counties: Orange

Project Benefits a Disadvantaged Community (or SDAC): Yes

Contribution SourcesContribution DateContribution Amount
  $638,604.45
Prop. 1, Ecosystem, Watershed Protection and Restoration11/14/2017$638,604.45


Project MetricMetric TopicQuantityUnit
Research/Planning (including Science)Feasibility Studies -- Ecosystem Restoration  

Water Action Plan Target

    
Protect and Restore Important EcosystemsAction Description