Project: Lukins Brothers Water Company Treatment Upgrades - Planning Project

Description: The scope of the project will include preparation of plans and specifications and environmental documentation for a granular activated carbon treatment system to address the PCE contamination in Lukins Bros WC water system. Other items included will be project management and the reimbursement of a preliminary engineering report (PER). The PER was completed as a result of the compliance order and has already been reviewed and approved by the Sacramento District Office. After discussions with the Sacramento District Office, for the sake of operation simplicity, Lukins Bros WC decided to select the GAC Treatment alternative rather than the UV/Membrane Treatment alternative originally selected in the PER.

Reference Number: 3940P01D1702005

Implemented By: Lukins Brothers Water Company

Objective: Planning project to design a GAC treatment plant to mitigate the PCE contamination problem in the Lukins Brothers Water Company's water system.

Type: Research/Planning (including Science)

Total Cost: $134,557.00

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 12/30/2018    Actual Completion:

Associated Counties: El Dorado

Project Benefits a Disadvantaged Community (or SDAC): Yes

Contribution SourcesContribution DateContribution Amount
  $134,557.00
Prop. 1, Water System Infrastructure Improvements - Safe Drinking Water11/27/2020$134,557.00


Project MetricMetric TopicQuantityUnit
Research/Planning (including Science)Other  

Water Action Plan Target

    
Provide Safe Water for All CommunitiesAction Description

Location