Project: Calpine Metering Project

Description: Calpine will install or replace water supply meters at approximately 140 connections. At each connection, a single service or double service assembly will be installed, and each meter will be furnished with a transmitter. The project will provide the meter reading equipment and software needed to collect water usage data.

Reference Number: 3940P01D1602052

Implemented By: Sierra County (Calpine) Waterworks District No. 1

Objective: The community does not meter water usage due to the lack of meters at most service connections. Existing water meters, where installed, are aged and inaccessible over winter months. The project will install/replace meters at all connections.

Type: Infrastructure Improvement

Total Cost: $374,063.00

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 12/1/2018    Actual Completion:

Associated Counties: Sierra

Project Benefits a Disadvantaged Community (or SDAC): Yes

Contribution SourcesContribution DateContribution Amount
  $374,063.00
Prop. 1, Water System Infrastructure Improvements - Safe Drinking Water11/27/2020$374,063.00


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementWater Quality Infrastructure  

Water Action Plan Target

    
Provide Safe Water for All CommunitiesAction Description