Project: Distribution System Improvements

Description: The Distribution System Improvement construction project replaces 26 manual control gates with automated control gates along with remote monitoring capability to provide system wide management and monitoring, and replaces over two miles of unlined earthen ditches with a pipeline to reduce seepage and provide the flexibility and infrastructure suitable for high efficiency irrigation systems. This project includes final design of all replacements, all work associated with reconstruction of head gates and pipe installations, and integration of automated controls into the existing SCADA system.

Reference Number: 3860-P01-113

Implemented By: Reclamation District 108

Objective:

Type: Infrastructure Improvement, Water Management

Total Cost: $3,000,000.00

Project Status: Project Implementation

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 8/21/2021    Actual Completion:

Associated Counties: Colusa, Yolo

Project Benefits a Disadvantaged Community (or SDAC): No

Contribution SourcesContribution DateContribution Amount
  $3,000,000.00
Local Contribution1/17/2017$1,500,000.00
Prop. 1, Water Conservation and Water Use Efficiency Plans, Projects, and Programs1/17/2017$1,500,000.00


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementOther  
Water ManagementConveyance  
Water ManagementWater Use Efficiency - Best Mgt. Practices  

Water Action Plan Target

    
Make Conservation a California Way of LifeAction Description
Increase Regional Self-Reliance and Integrated Water Management Across All Levels of GovernmentAction Description
Manage and Prepare for Dry PeriodsAction Description

Location

loading loading