Project: Amador Regional Sanitation Aurthority Sewer Improvement and Recycling - Planning Project

Description: Replace aged and unsafe AC pipe preventing environmental disaster with breaks and leaks, replace irrigation system with high velocity water guns to discharge more effluent to meet 100 year flood requirement, add electrical power to convert gravity system with pressurized system, develop new irrigation sites for recycled water offsetting the use of clean water for agricultural use, build renewable energy system to offset energy usage, build proper sized SCADA System for auto response and emergency alarms. Remove contaminated pond solids to prevent contamination of ground and surface water for the safety and health of the surrounding communities.

Reference Number: 3940P01D1604024

Implemented By: Amador Regional Sanitation Authority

Objective: Evaluate alternatives that will address long term storage requirements, additional recycling locations, improvements in safety and environmental security, and the replacement of the Henderson Reservoir outfall pipeline.

Type: Infrastructure Improvement

Total Cost: $63,658.00

Project Status: Withdrawn

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 2/28/2019    Actual Completion: 7/23/2019

Associated Counties: Amador

Project Benefits a Disadvantaged Community (or SDAC): Yes

Contribution SourcesContribution DateContribution Amount
  $63,658.00
Prop. 1, State Water Pollution Control Revolving Fund - Wastewater Treatment Projects8/15/2018$63,658.00


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementOther  

Water Action Plan Target

    
Provide Safe Water for All CommunitiesAction Description