Project: Lake Camanche Water System Compliance - Construction Project

Description: Amador Water Agency will construct a new 500,000 gallon storage tank. The new tank, which will be located at the existing tank 9 site, will allow the system to achieve its required chlorine contact time. Amador Water Agency will also install approximately 3,100 feet of 12-inch PVC pipeline to connect the new tank to the existing distribution system near Well 14. The existing 8-inch line that runs from the distribution system to the tank site will serve as the new tank?s inlet, while the new line will serve as its outlet. This project will also help their pressure and supply issues.

Reference Number: 3940P01D1602019

Implemented By: Amador Water Agency

Objective: Amador Water Agency will construct a new 500,000 gallon storage tank to achieve its required chlorine contact time and address supply issues. Approximately 3,100 feet of 12-inch PVC will be installed to connect the new tank to the distribution system.

Type: Infrastructure Improvement

Total Cost: $1,824,092.00

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 7/1/2018    Actual Completion: 12/5/2018

Associated Counties: Amador

Project Benefits a Disadvantaged Community (or SDAC): Yes

Contribution SourcesContribution DateContribution Amount
  $1,824,092.00
Other State Funds10/2/2018$47,868.44
Prop. 1, Water System Infrastructure Improvements - Safe Drinking Water1/25/2019$1,776,223.56


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementOther  

Water Action Plan Target

    
Provide Safe Water for All CommunitiesAction Description