Project: Amador Water Agency - Construction Project

Description: Amador Water Agency intends to add aluminum chlorohydrate (ACH) coagulation to reduce the levels of Total Organic Carbon, which will reduce levels of Disinfection Byproducts (DBP) throughout the distribution system and get the system back into compliance with the Stage 2 DBP rule. Amador Water Agency will also install a plate settler, a Deskins drying bed system, and a backwash recycle pump station to replace their existing backwash recovery skid. The plant will recycle 100% of its backwash, and Amador Water Agency will transfer its solid waste from the drying beds to a landfill.

Reference Number: 3940P01D1602018

Implemented By: Amador Water Agency

Objective: Amador Water Agency will modify its treatment process with the addition of aluminum chlorohydrate to reduce levels of disinfection byproducts in the distribution system. The backwash recovery skid will also be replaced with a more efficient system.

Type: Infrastructure Improvement

Total Cost: $2,699,560.01

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 7/1/2018    Actual Completion:

Associated Counties: Amador

Project Benefits a Disadvantaged Community (or SDAC): Yes

Contribution SourcesContribution DateContribution Amount
  $2,699,560.01
Prop. 1, Water System Infrastructure Improvements - Safe Drinking Water11/27/2020$2,699,560.01


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementOther  

Water Action Plan Target

    
Provide Safe Water for All CommunitiesAction Description