Project: Maywood Avenue Well Improvements - Planning Project

Description: The Maywood Avenue Well Improvement project will restore the drinking water quality to the area serviced by Maywood Mutual No. 2 (MMWNo.2) so that the residents have a safe, clean and reliable source of drinking water. The project consists of constructing an Iron and Manganese treatment plant. Currently, a planning study is underway in order to prioritize and set budgets for the necessary improvements. The planning study will recommend a cost effective strategy for restoring well water quality to the area serviced by MMWNo. 2 and reduce the costly dependence on imported water. The recommended solution will include three elements: a wellhead treatment system, recommended improvements for public safety, and recommended improvements for operator safety and efficiency.

Reference Number: 3940P01D1602029

Implemented By: Maywood Mututal Water Company #2

Objective: The planning study will recommend a cost effective strategy for restoring well water quality to the area serviced by MMWNo. 2 and reduce the costly dependence on imported water.

Type: Research/Planning (including Science)

Total Cost: $223,895.00

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 5/1/2017    Actual Completion: 3/1/2018

Associated Counties: Los Angeles

Project Benefits a Disadvantaged Community (or SDAC): Yes

Contribution SourcesContribution DateContribution Amount
  $223,895.00
Prop. 1, Water System Infrastructure Improvements - Safe Drinking Water7/6/2018$223,895.00


Project MetricMetric TopicQuantityUnit
Research/Planning (including Science)Other  

Water Action Plan Target

    
Provide Safe Water for All CommunitiesAction Description