Project: River Pines PUD Storage and Distribution Rehab - Construction Project

Description: The water system is aged and faces numerous infrastructure needs. The project will replace small diameter water mains, construction pressure reducing valves, replace fire hydrants and water meters, and replace the storage tank.

Reference Number: 3940P01D1602043

Implemented By: River Pines Public Utility District

Objective: The water system is aged and faces numerous infrastructure needs. This project includes the engineering needed to replace small diameter water mains, construct pressure reducing valves, replace fire hydrants and water meters, and replace a storage tank.

Type: Infrastructure Improvement

Total Cost: $435,394.00

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 3/1/2018    Actual Completion: 6/6/2018

Associated Counties: Amador

Project Benefits a Disadvantaged Community (or SDAC): Yes

Contribution SourcesContribution DateContribution Amount
  $435,394.00
Prop. 1, Water System Infrastructure Improvements - Safe Drinking Water11/27/2020$435,394.00


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementOther  

Water Action Plan Target

    
Provide Safe Water for All CommunitiesAction Description