Project: Fresno, City of- Recycled Water Distribution System Southwest Quadrant

Description: The proposed project includes the design and construction of a pipeline and booster pump station to convey tertiary treated recycled water from the RWRF for landscape irrigation in the City's Southwest Quadrant.

Reference Number: 3940P01D1501011

Implemented By: Fresno, City of

Objective: Construct a pipeline and booster pump in the Southwest Quadrant

Type: Water Management

Total Cost: $70,600,000.00

Project Status: Project Implementation

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 6/30/2021    Actual Completion:

Associated Counties: Fresno

Project Benefits a Disadvantaged Community (or SDAC): No

Contribution SourcesContribution DateContribution Amount
  $70,600,000.00
Other State Funds2/28/2020$55,600,000.00
Prop. 1, Water Recycling4/5/2016$15,000,000.00


Project MetricMetric TopicQuantityUnit
Water ManagementWater Use Efficiency - Recycling  

Water Action Plan Target

    
Increase Regional Self-Reliance and Integrated Water Management Across All Levels of GovernmentAction Description

Location