Project: Santa Cruz Mid-County Groundwater Management Program

Description: The objective of this project is to inform the development of a Groundwater Sustainability Plan through the following tasks: form a GSA, provide more outreach and services to private pumpers, update three ordinances to address current impacts of over-pumping, enhance the comprehensive groundwater model for the Mid-County Groundwater Basin, fill data gaps, identify recharge projects, and assess the impact on the basin of different pumping classes to help inform future policies.

Reference Number: 3860-P01-068

Implemented By: Santa Cruz County

Objective: Sustainable Groundwater Planning

Type: Water Management

Total Cost: $506,777.00

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 6/30/2019    Actual Completion: 12/31/2019

Associated Counties: Santa Cruz

Project Benefits a Disadvantaged Community (or SDAC): No

Contribution SourcesContribution DateContribution Amount
  $506,777.00
Local Contribution2/17/2016$257,777.00
Prop. 1, Groundwater Plans and Projects2/17/2016$249,000.00


Project MetricMetric TopicQuantityUnit
Water ManagementOther  

Water Action Plan Target

    
Increase Regional Self-Reliance and Integrated Water Management Across All Levels of GovernmentAction Description

Location

loading loading