Project: Greater Los Angeles County: Calleguas-Las Virgenes Municipal Water Districts Interconnection Project

Description: This Project constructs a potable intertie pipeline (5,600 linear feet of 24-inch pipe) for up to 2,170 AFY of increased water supply availability and a recycled water pipeline (along the same alignment) serving 13 AFY.

Reference Number: 3860-P84-1408

Implemented By: Los Angeles County Flood Control District

Objective: Project will help local public agencies to meet long-term water supply needs, protection of water quality, and augment/restore environmental conditions.

Type: Infrastructure Improvement

Total Cost: $9,207,384.00

Project Status: Project Implementation

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 3/31/2021    Actual Completion:

Associated Counties: Los Angeles

Located In Disadvantaged Community: No

Contribution SourcesContribution DateContribution Amount
  $9,207,384.00
Local Contribution4/21/2016$7,231,867.00
Prop. 84, Integrated Regional Water Management4/21/2016$1,975,517.00


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementWater Quality Infrastructure  