Project: Westside: Grant Administration

Description: Work related to the application and grant management activities.

Reference Number: 3860-P84-1479

Implemented By: Solano County Water Agency

Objective: Project will help local public agencies to meet long-term water supply needs, protection of water quality, and augment/restore environmental conditions.

Type: Other

Total Cost: $70,542.71

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 10/1/2019    Actual Completion: 6/12/2020

Associated Counties: Yolo

Located In Disadvantaged Community: No

Contribution SourcesContribution DateContribution Amount
  $70,542.71
Prop. 84, Integrated Regional Water Management11/1/2021$70,542.71



Location