Project: Lanare Community Services District - Tito Balling (Receiver)

Description: Arsenic exeedance - remediation project. Install two new water supply wells - The existing Arsenic treatment plant designed by Boyle Engineering and put into service in 2006 works. It is the water production and use that were out of control thus placing the cost of operation of the treatment plant out of control. A separate USDA project to install meters, establish a tiered rate and guarantee sufficient income to run the arsenic treatment plant is currently in progress. Once the meter project is completed the next step is to re-establish the treatment plant. This project is to reactivate the existing arsenic treatment plant. Pumps, hoses, injectors, filters and tanks will need to be cleaned and or replaced as well as supplies testing and support.

Reference Number: 3940D1503001

Implemented By: Lanare Community Services District

Objective: Install two new water supply wells - The existing Arsenic treatment plant designed by Boyle Engineering and put into service in 2006 works. It is the water production and use that were out of control thus placing the cost of operation of the treatment plant out of control. A separate USDA project to install meters, establish a tiered rate and guarantee sufficient income to run the arsenic treatment plant is currently in progress. Once the meter project is completed the next step is to re-establish the treatment plant. This project is to reactivate the existing arsenic treatment plant. Pumps, hoses, injectors, filters and tanks will need to be cleaned and or replaced as well as supplies testing and support.

Total Cost: $3,420,000.00

Project Status: Project Implementation

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 6/30/2022    Actual Completion:

Associated Counties: Fresno

Located In Disadvantaged Community: Unknown

Contribution SourcesContribution DateContribution Amount
  $3,420,000.00
Prop. 84, Small Community Infrastructure Improvements Program12/29/2015$3,420,000.00