Project: Emergency Project for FCSA#30 - El Provenir (Oral Agreement)

Description: The project was to haul water as interim water supply while repairing the raw water transmission line.

Reference Number: 3940P84E1000019001

Implemented By: County of Fresno

Objective: The objective is to provide interim water supply while repairing the raw water transmission line and restoring water service.

Type: Infrastructure Improvement

Total Cost: $9,712.66

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 9/11/2014    Actual Completion: 4/7/2015

Associated Counties: Fresno

Located In Disadvantaged Community: Yes

Contribution SourcesContribution DateContribution Amount
  $9,712.66
Prop. 84, Emergency Safe Drinking Water Supply Program8/17/2015$9,712.66


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementOther  