Project: Shasta County Department of Public Works CSA 17 Cottonwood- Collection and Treatment Improvement

Description: The Project will include planning for repair/replacement of approximately 2,500 feet of aging collection system mains, replacement of equipment that has met its useful service life (lift station pumps, mechanical, and emergency generators, etc.) and improvements at the wastewater treatment plant (WWTP).

Reference Number: 3940P01D1504002

Implemented By: Shasta County Department of Public Works CSA 17 Cottonwood

Objective: Planning project to determine repairs for WWTP

Type: Infrastructure Improvement

Total Cost: $350,309.00

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 5/31/2017    Actual Completion: 6/15/2017

Associated Counties: Shasta

Project Benefits a Disadvantaged Community (or SDAC): Yes

Contribution SourcesContribution DateContribution Amount
  $350,309.00
Prop. 1, State Water Pollution Control Revolving Fund - Wastewater Treatment Projects6/29/2017$350,309.00


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementWater Quality Infrastructure  

Water Action Plan Target

    
Increase Operational and Regulatory EfficiencyAction Description