Project: Woodland Study and Preliminary Design

Description: Provides limited funding for preliminary design activities focusing on the Local Preferred Plan or a bypass channel from Cache Creek around the south side of the settling basin (currently under study by the USACE).  Other aspects of the projects may be considered as systemwide elements. Total project amount includes State support costs for project implementation.

Reference Number: 3860-P1E-895

Implemented By: City of Woodland

Objective: Flood Protection

Type: Research/Planning (including Science)

Total Cost: $1,742,873.59

Project Status: Project Implementation

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 6/30/2022    Actual Completion:

Associated Counties: Sacramento



Contribution SourcesContribution DateContribution Amount
  $1,742,873.59
Prop. 1E, Urban Flood Risk Reduction Program6/8/2015$1,742,873.59


Project MetricMetric TopicQuantityUnit
Research/Planning (including Science)Feasibility Studies -- Flood Control/Water Supply  