Project: Berkeley Bay Trail Extension: Shoreline Access and Trail Staging Area

Description: Funds will be used to construct a 375 linear foot extension of the Berkeley Bay Trail (Bay Trail Spur), improvement of 1.5 acre area of east parking lot and windsurf launch, improve drainage, add bioswales, inc. trash receptables, lighting, traffic striping.

Reference Number: 37601400301

Implemented By: City of Berkeley

Objective: public access

Type: Recreation/Access/Interpretation

Total Cost: $500,000.00

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 3/30/2019    Actual Completion: 2/12/2019

Associated Counties: Alameda

Located In Disadvantaged Community: No

Contribution SourcesContribution DateContribution Amount
  $500,000.00
Prop. 84, San Francisco Bay Area Conservancy Program12/22/2014$500,000.00


Project MetricMetric TopicQuantityUnit
Recreation/Access/InterpretationNew/enhanced public parks  
Recreation/Access/InterpretationTrail construction/Improvement0.73miles of trail constructed/improved