Project: Construction project for City of Los Angeles

Description: Installation of 6,400 linear feet of 84-inch and 96-inch diameter steel pipe, valves, and flow meters to supply proposed Headworks Reservoir.

Reference Number: 3940SRF1910067034C

Implemented By: City of Los Angeles

Objective: SRF State Match

Type: Infrastructure Improvement

Total Cost: $64,769,179.00

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 6/25/2015    Actual Completion: 12/23/2014

Associated Counties: Los Angeles

Located In Disadvantaged Community: Yes

Contribution SourcesContribution DateContribution Amount
  $64,769,179.00
Federal Contribution6/11/2014$47,598,913.50
Prop. 50, Drinking water infrastructure - bal/Cal8/12/2013$753,463.53
Prop. 84, Safe Drinking State Revolving Fund Program6/11/2014$16,416,801.97