Project: Construction project for Pratt Mutual Water Company

Description: Construction project - Consolidation project

Reference Number: 3940P8413C129

Implemented By: Pratt Mutual Water Company

Objective: Funding of a project, which includes engineering design, to identify options to address and resolve water quality issues

Type: Infrastructure Improvement

Total Cost: $4,808,399.38

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 5/31/2017    Actual Completion: 7/25/2017

Associated Counties: Tulare

Located In Disadvantaged Community: Yes

Contribution SourcesContribution DateContribution Amount
  $4,808,399.38
Prop. 84, Small Community Infrastructure Improvements Program2/20/2014$2,512,578.34
Prop. 84, Small Community Infrastructure Improvements Program6/5/2015$2,295,821.04


Project MetricMetric TopicQuantityUnit
Infrastructure ImprovementOther  

Location

loading loading