Project: North Coast: Salyer Mutual Water Company, Distribution System and Hydrants

Description: Replace existing distribution system lines (approximately 10,000 feet) with new 4- to 6- inch PVC piping and connection with residential units, install fire hydrants and isolation and pressure control valves.

Reference Number: 3860-P84-1047

Implemented By: County of Humboldt

Objective: Project will help local public agencies to meet long-term water supply needs, protection of water quality, and augment/restore environmental conditions.

Type: Water Management

Total Cost: $209,999.09

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 6/30/2019    Actual Completion: 1/1/2017

Associated Counties: Del Norte, Humboldt, Mendocino, Modoc, Siskiyou, Sonoma, Trinity

Located In Disadvantaged Community: Yes

Contribution SourcesContribution DateContribution Amount
  $209,999.09
Prop. 84, Integrated Regional Water Management5/4/2018$209,999.09


Project MetricMetric TopicQuantityUnit
Water ManagementConveyance  