Project: Santa Ana: Arlington Desalter Interconnection Project (C. Corona)

Description: Construct two-way inter-tie connecting portion of City of Corona Department system with Western Municipal Water District’s system to improve water supply reliability.

Reference Number: 3860-P84-985

Implemented By: Santa Ana Watershed Project Authority

Objective: Project will help local public agencies to meet long-term water supply needs, protection of water quality, and augment/restore environmental conditions.

Type: Water Management

Total Cost: $1,348,049.00

Project Status: Complete but Not Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 6/30/2019    Actual Completion: 8/21/2014

Associated Counties: Orange, Riverside, San Bernardino

Located In Disadvantaged Community: No

Contribution SourcesContribution DateContribution Amount
  $1,348,049.00
Local Contribution11/21/2011$948,049.00
Prop. 84, Integrated Regional Water Management11/21/2011$400,000.00


Project MetricMetric TopicQuantityUnit
Water ManagementConveyance  
Water ManagementWater Use Efficiency - Best Mgt. Practices  