Project: SF Bay Area: South Bay Advanced RW Treatment, Reverse Osmosis

Description: Construct a 10 mgd recycled water treatment facility using micro-filtration, reverse osmosis, and ultraviolet disinfection treatment to purify reclaimed water to produce high quality recycled water.

Reference Number: 3860-P84-835

Implemented By: Bay Area Clean Water Agencies

Objective: Project will help local public agencies to meet long-term water supply needs, protection of water quality, and augment/restore environmental conditions.

Type: Water Management

Total Cost: $7,676,700.00

Project Status: Complete and Fully Paid

On Time?: Yes    Within Scope?: Yes    Within Budget?: Yes

Estimated Completion: 12/31/2017    Actual Completion: 5/31/2015

Associated Counties: Alameda, Contra Costa, Marin, Napa, San Francisco, San Mateo, Santa Clara, Solano, Sonoma

Located In Disadvantaged Community: Yes

Contribution SourcesContribution DateContribution Amount
  $7,676,700.00
Local Contribution11/21/2011$5,191,700.00
Prop. 84, Integrated Regional Water Management11/21/2011$2,485,000.00


Project MetricMetric TopicQuantityUnit
Water ManagementConveyance  
Water ManagementWater Use Efficiency - Recycling  